Kwasi Amoako-Atta (3rd from left), Minister of Roads and Highways, with technical staff at the the Dome-Kitase road project site
Kwasi Amoako-Atta (3rd from left), Minister of Roads and Highways, with technical staff at the the Dome-Kitase road project site

Dome-Kitase road project ahead of schedule - Contractor

The Executive Chairman of First Sky Construction Limited, Eric Seedy Kutortse, has given an assurance that his company will complete the Dome-Kitase Road Rehabilitation Project under 20 months.

That, he said, was because the construction of the 23-kilometre stretch, which commenced in July this year and scheduled to be completed in two years, was already about 30 per cent completed.

Advertisement

“What we are doing currently is that we are improving the vertical alignment of the road by cutting to formation, and once that is done, the project will be almost 30 per cent completed.

“So per our programme, by the end of this month we will cut the entire road to formation,” he added.

Mr Kutortse gave the assurance when the Minister of Roads and Highways, Kwasi Amoako-Atta, visited the project site as part of his routine inspection of ongoing road projects in the country.

The minister was accompanied by the Eastern Regional Minister, Seth Acheampong, and some senior officials and engineers from the ministry, the Ghana Highway Authority, the Department of Feeder Roads and chief executives of some municipal/district assemblies who had jurisdiction over the project area.

Mr Kutortse said the company was determined to provide good, quality road infrastructure to accelerate the socio-economic development of the area and the country as a whole in spite of working ahead of time.

Commendation  Mr Amoako-Atta said he was impressed with the progress of work, and lauded First Sky Limited for the company’s seriousness towards the project.

“I like what I have seen, and from the briefings that I have had from all the engineers up to the Chief Director who have the technical eye, the construction is according to specifications,” he said.

“It was supposed to be completed in 24 months, but it is in capable hands, our own and one of the best in the country, so I trust him,” he added.

He encouraged the company to prioritise the safety of its workers and motorists during the construction process to avoid any incidents.

Project scope

The GH¢195 million project, which will cover 23 kilometres, begins from the Dome Roundabout in the Greater Accra Region, through Berekuso and ends in Kitase, both in the Eastern Region.

It includes a 16.3km two-lane single carriageway with asphaltic concrete surfacing; a 2.8km asphaltic concrete surfacing dual carriageway arterial with auxiliary lanes on both sides for drop off/pick up; and a one-km two-lane single carriageway for Ashesi University, also with asphaltic concrete surfacing.

Part of the Ofankor-Nsawam road under construction

The stretch will connect the Accra-Kumasi Road to the Accra-Aburi-Koforidua Road, and provide an alternate route for road users between Accra and Aburi.

Mr Amoako-Atta also visited the Ofankor-Nsawam Road Rehabilitation Project where he expressed satisfaction with the current state of the project.

The scheduled works on the 33.4 km stretch, which forms part of the Accra-Kumasi road network, is expected to last two years, ending in July 2024.

The project being undertaken by Messrs Maripoma Enterprise Limited for GH¢341.48 million will consist of the reconstruction of the existing asphaltic concrete pavement and about nine pedestrian crossing facilities, and four interchanges at Amasaman, Kpobiman, Medie and Nsawam Junction with streetlights.

The road — currently a two-lane dual carriageway — is being expanded to a three-lane dual carriageway, with service lanes. It will also have adequate drainage structures, traffic signs and road markings.

Some structures and buildings affected by the project have been marked for demolition.

Mr Amoako-Atta took time to engage with owners of such structures, and assured them of adequate compensation in due course.

 