Contract for Accra-Tema Motorway expansion signed

Contract for Accra-Tema Motorway expansion signed

The Ministry of Roads & Highways has announced that it has signed a contract with Portuguese conglomerate Mota-Engil, Engenharia E Constructao Africa S. A for the design and construction of the Accra-Tema Motorway and Extensions Project.

A press release signed by the Minister of Roads & Highways, Kwasi Amoako-Attah said the contract was signed on December 16, 2020, after the approval of the Public Procurement Authority and the Central Tender Review Board.

The release added that "Actual construction works will commence soon after the detailed design has been approved and relocation of services are completed".

Related Articles

Govt places embargo on new contracts exceeding GH₵2million

Final blockade of Motorway illegal U-turns begins

'Motorway accident beer party' and road traffic accidents!

Unapproved U-turns on Accra-Tema motorway being blocked [PHOTOS]

'Free booze frenzy' on Accra-Tema motorway as beer truck accident reportedly claims one life [VIDEO]

Aerial view of new Tema Motorway Interchange - VIDEO

Scope of contract

As part of the contract, the release said the existing 19.5kilometre motorway is to be reconstructed and expanded into a two-lane dual carriageway for the freeway and a three-lane dual carriageway for the urban highway. The freeway will remain concrete surfacing whilst the urban highway will be in asphaltic concrete with paved shoulders.

The Tetteh Quarshie Interchange - Apenkwa Interchange (5.7km) is also to be reconstructed into a 6-lane dual carriageway with asphaltic concrete surfacing while the Tesano Junction - Neoplan Junction (2.5km) will be reconstructed into a three-lane dual carriageway in asphaltic concrete surfacing.

Additionally, Mota Engil is to construct five new interchanges at Lashibi, Community 18 Junction, Teshie Link Junction, Dzorwulu Junction and Neoplan Junction to facilitate traffic movement at the junctions, remodel the Tetteh Quarshie Interchange to eliminate congestion, provide streetlights and construct toll booths.

The Portuguese construction company is also tasked with reconstructing the Apenkwa interchange, rehabilitating the Achimota Interchange and constructing 14 new pedestrian footbridges.

Read the entire release below;

DESIGN AND CONSTRUCTION OF ACCRA – TEMA MOTORWAY AND EXTENSIONS PROJECT (ATMP) 27.7KM

PRESS RELEASE

The Government of Ghana, through the Ministry of Roads and Highways, is happy to announce that the contract for the Design and Construction of the Accra-Tema Motorway and Extensions Project, from the Tema Interchange through Apenkwa Interchange to Neoplan Junction, was signed on 16th December 2020 with Mota-Engil, Engenharia E Construcao Africa SA, after the approval of the Public Procurement Authority and the Central Tender Review Board.

The scope of works under the contract includes the following:
1) the reconstruction and expansion of the existing Motorway(19.5km) into a two-lane Dual Carriageway for the freeway, and a three-lane dual carriageway for the urban highway. The freeway will remain concrete surfacing, whilst the urban highway will be in asphaltic concrete with paved shoulders;
2) the reconstruction of the Tetteh Quarshie Interchange to Apenkwa Interchange (5.7km) into a six-lane dual carriageway with Asphaltic Concrete surfacing;
3) reconstruction of Tesano Junction – Neoplan Junction (2.5km) into a three-lane dual carriageway in asphaltic concrete surfacing;
4) construction of five (5) new interchanges at Lashibi, Community 18 Junction, Teshie Link Junction, Dzorwulu Junction and Neoplan Junction to facilitate traffic movement at the junctions;
5) remodeling of the Tetteh Quarshie Interchange to eliminate the perennial congestion;
6) reconstruction of Apenkwa Interchange;
7) rehabilitation of Achimota Interchange;
8) provision of streetlights;
9) construction of fourteen (14) new pedestrian footbridges to ensure safe crossing of pedestrians, where necessary; and
10) construction of Toll plazas:

Actual construction works will commence immediately after the detailed design has been approved, and relocation of services are completed. The Employer during this time will also be engaging stakeholders and persons affected by the project to ensure all issues are resolved.

The Ghana Highway Authority is the implementing agency, and the public may contact the Public Affairs Division of the Authority for any further clarification.

SIGNED
KWASI AMOAKO-ATTAH (MP)
MINISTER